Coefficient of Consolidation calculation

Problem: A 3m layer double drainage of saturated clay under surcharge loading underwent 90% consolidation in 75 days. Find the coefficient of consolidation?



Solution:
We know,
            Tv= Cvt /  Hdr2

      Here,  Tv= 0.848 (for 90% consolidation)
                   t = 75 days
               Hdr = (3/2) m (for double drainage)
                Cv = ?

                 Cv= 0.848* (3/2)2/ 75
                      = 0.025 m2/day
                      = 2.894 * 10-7 m2/s
Answer: 2.894 * 10-7 m2/s